Project Management Key Ideas 1. A project is a set of activities or specialized functions all directed toward achieving a unique objective or goal. 2. A network diagram is a graphic representation of a project that that shows major project activities. It is made up of arrows and nodes. The arrows indicate sequential relationships among activities. This information is extremely important for project planning, for time and cost estimation, and for allocating resources. (AON). In AOA diagrams, the arrows represent activities and the nodes represent the beginning and/or ending of activities. In AON diagrams, activities are represented by nodes, and the arrows simply indicate the direction of sequential relationships. A path is a sequence of activities beginning with the first node and ending with the last node. The path with the longest set of times is called the critical path, and the activities on that path are called criticalactivities. The term critical refers to timely project completion; if any activities on the critical path take more time than expected, and the increased time isn?t offset by a decrease somewhere else in that path, the project duration will increase. 3. AOA networks sometimes require the use of a dummy activity to clarify relationships. These zero-time activities are represented by a dashed arrow. A dummy activity would be used, for example, when two (or more) activities have some, but not all, predecessors in common. See the last diagram on the left side of Table 18-1 (p. 778) of your textbook. 4. Some A0A diagrams include dummy activities. These zero-time activities, represented by dashed lines, are used to clarify relationships. One use is where two activities both begin and end at the same node. Another use is where two activities have some but not all predecessors in common. 5. For deterministic time estimates, the algorithm for finding the critical path involves two passes through the data: first, a forward pass to find the early start (ES) and early finish (EF) times for each activity, and then a backward pass to find the late finish (LF) and late start (LS) times. The critical path is the path for which ES = LS and EF = LF for every member of that path. The slack time is the difference between LS and ES. Thus the activities on the critical path all have zero slack. The critical path duration is equal to the project duration. For the forward pass, assign the time zero to the starting node. This is the ES of every activity emanating from the source; the EF is the time t of completion. The general formula for ES is: ES = largest early completion time, EF, of all immediately preceding
activities
6. Probabilistic PERT introduces uncertainty into a PERT model. For each activity there are three time estimates:
(1) The variance of activity completion time is Assuming there is just a single critical path and there are no parallel critical
paths, the expected time for completion of the project is the sum of times In order to find the probability of completing the project in any specified
time, Look up the probability in the table of areas under the normal curve. For example, if z =1.96, the probability of completion is 97.5 percent (look up z = 1. 96in Appendix Table B). If there are multiple independent paths with probabilistic time estimates, use the approach described in Examples 5 and 6 and Solved Problem 3 in the text. 7. Shortening the time for completion can reduce costs and enhance profitability in several ways: (1) Indirect, or supervision, costs are reduced. Under these conditions, it is worthwhile to incur some increases in direct costs to attain the benefits of reducing the total time by crashing the project. Give priority to those critical path activities that have the lowest cost per day in crashing. Rank the critical activities in order of lowest per day crashing cost. Assign funds available for crashing successively to the lowest cost per day until either those funds are all used up or the desired schedule is obtained. Crashing can reduce slack time on noncritical activities. Therefore, it may happen that as you begin to crash, the slack times for activities on noncritical paths reduce to a point where they become critical too. This results in parallel critical paths. You can continue crashing beyond this point, but only by crashing all parallel paths. 8. PERT has the advantage of forcing managers to organize and quantify the decision-making process. The graphs, tables, and critical path calculations are helpful in showing up how the organization fits together and where to move resources around to achieve the best possible results. For large projects, PERT must be computerized. 9. Key decisions in project management include deciding which projects to implement, choosing a project manager, assembling a project team, designing the project, managing and controlling resources, and deciding if, and when, an ongoing project should be terminated. 10. Project managers are responsible for managing the work, human resources, communications, quality, time, and costs. They are also responsible for risk management. Risks include unforeseen circumstances that can negatively impact the project. Risk is highest early in a project, but the cost to overcome the occurrence of a risk event is highest near the end of the project. | ||||||
|