 |
1 |  |  Project analysis includes the following procedures: |
|  | A) | Sensitivity analysis |
|  | B) | Break-even analysis |
|  | C) | Monte Carlo simulation |
|  | D) | All of the above |
 |
 |
2 |  |  After the completion of project analysis, the final decision on the project would be from: |
|  | A) | Sensitivity analysis |
|  | B) | Break-even analysis |
|  | C) | Decision trees |
|  | D) | NPV |
 |
 |
3 |  |  You are given the following data for year 1: Revenues = 120, Fixed costs = 30; Total variable costs = 50; Depreciation = $10; Tax rate = 30%. Calculate the after tax cash flow for the project for year 1. |
|  | A) | $31 |
|  | B) | $21 |
|  | C) | $30 |
|  | D) | None of the above |
 |
 |
4 |  |  A project has the following cash flows: C0 = -100,000; C1 = 50,000; C2 = 150,000; C3 = 100,000. If the discount rate changes from 12% to 13%, what is the change in the NPV of the project(approximately)? |
|  | A) | 4375 decrease |
|  | B) | 4375 increase |
|  | C) | 122,650 increase |
|  | D) | 131,025 decrease |
 |
 |
5 |  |  Eble Company proposes to invest $6 million in a new type of text printing equipment. The fixed costs are $0.5 million per year. The equipment is expected to last for 5 years. The manufacturing costs per hammer is $1. Calculate the break-even volume per year. (Ignore taxes.) |
|  | A) | 400,000 |
|  | B) | 500,000 |
|  | C) | 250,000 |
|  | D) | None of the above |
 |
 |
6 |  |  Monte Carlo simulation is a tool for considering the: |
|  | A) | Effect of changing one variable on the NPV of the project |
|  | B) | Effect of changing a limited number of plausible combination of variables on the NPV of the project |
|  | C) | Effect of changing all possible combinations of variables on the NPV of the project |
|  | D) | None of the above |
 |
 |
7 |  |  Which of the following simulation outputs is likely to be most useful and easy to interpret? The output shows the distribution(s) of the project: |
|  | A) | Earnings |
|  | B) | Internal rate of return |
|  | C) | Cash flows |
|  | D) | Profits |
 |
 |
8 |  |  The following statements about simulation models are true except: |
|  | A) | Simulation models enable the financial manager to analyze risky projects without estimating the approximate cost of capital |
|  | B) | Simulation models are complex and expensive to develop |
|  | C) | Simulation models are specific to the project and every project requires a new simulation model |
|  | D) | Simulation models usually ignore opportunities to expand or abandon the project |
 |
 |
9 |  |  Generally, the simulation models for projects are developed using a: |
|  | A) | Computer |
|  | B) | Roulette wheel |
|  | C) | Pair of dice |
|  | D) | Pack of cards |
 |
 |
10 |  |  Monte Carlo simulation is likely to be most useful: |
|  | A) | For simple problems |
|  | B) | For problems of moderate complexity |
|  | C) | For very complex problems |
|  | D) | Regardless of the problem's complexity |
 |
 |
11 |  |  The following is not among the steps involved in the Monte Carlo method: |
|  | A) | Modeling the project |
|  | B) | Specifying the numbers on the roulette wheel |
|  | C) | Specifying probabilities |
|  | D) | Simulating the cash flows |
 |
 |
12 |  |  The hardest and most important part of a simulation is: |
|  | A) | Simulating the cash flows |
|  | B) | Specifying the inter-dependencies |
|  | C) | Specifying probabilities |
|  | D) | Specifying the numbers on the roulette wheel |
 |
 |
13 |  |  When conducting a sensitivity analysis, variables are set one at a time to their optimistic and pessimistic values. |
|  | A) | True |
|  | B) | False |
 |
 |
14 |  |  The break-even point in terms of EAC flows is usually lower than the break-even point on an accounting basis. |
|  | A) | True |
|  | B) | False |
 |
 |
15 |  |  Monte Carlo simulation is a tool for considering all possible combinations of variables. |
|  | A) | True |
|  | B) | False |
 |