 |
| 1 |  |  Proactive risk management is sometimes described as fire fighting. |
|  | A) | True |
|  | B) | False |
|
|
 |
| 2 |  |  Software risk always involves two characteristics |
|  | A) | fire fighting and crisis management |
|  | B) | known and unknown risks |
|  | C) | uncertainty and loss |
|  | D) | staffing and budget |
|
|
 |
| 3 |  |  Three major categories of risks are |
|  | A) | business risks, personnel risks, budget risks |
|  | B) | project risks, technical risks, business risks |
|  | C) | planning risks, technical risks, personnel risks |
|  | D) | management risks, technical risks, design risks |
|
|
 |
| 4 |  |  Generic risks require far more attention than product-specific risks. |
|  | A) | True |
|  | B) | False |
|
|
 |
| 5 |  |  A risk item checklist would contain known and predictable risks from which of these categories? |
|  | A) | product size |
|  | B) | development environment |
|  | C) | staff size |
|  | D) | process definition |
|  | E) | all of the above |
|
|
 |
| 6 |  |  Questions that should be asked to assess the overall project risk include: |
|  | A) | Have top managers formally committed to support the project? |
|  | B) | Are end-users committed to the project and proposed system being built? |
|  | C) | Are requirements fully understood by development team and customers? |
|  | D) | Does the proposed budget have time allocated for marketing? |
|  | E) | a, b and c |
|
|
 |
| 7 |  |  Software risk impact assessment should focus on consequences affecting |
|  | A) | planning, resources, cost, schedule |
|  | B) | marketability, cost, personnel |
|  | C) | business, technology, process |
|  | D) | performance, support, cost, schedule |
|
|
 |
| 8 |  |  Risk projection attempts to rate each risk in two ways |
|  | A) | likelihood and size |
|  | B) | likelihood and probability |
|  | C) | likelihood and impact |
|  | D) | likelihood and mitigation |
|
|
 |
| 9 |  |  Risk tables are sorted by |
|  | A) | probability and cost |
|  | B) | probability and impact |
|  | C) | probability and size |
|  | D) | probability and exposure |
|
|
 |
| 10 |  |  Individual team members can make their own estimate for a risk probability and then develop a consensus value. |
|  | A) | True |
|  | B) | False |
|
|
 |
| 11 |  |  Which factors affect the probable consequences likely if a risk does occur? |
|  | A) | risk cost |
|  | B) | risk timing |
|  | C) | risk scope |
|  | D) | risk resources |
|  | E) | both b and c |
|
|
 |
| 12 |  |  A risk referent level is a risk component value (performance, cost, support, schedule) or combination of values that cause a project to be terminated. |
|  | A) | True |
|  | B) | False |
|
|
 |
| 13 |  |  The reason for refining risks is to break them into smaller units having different consequences. |
|  | A) | True |
|  | B) | False |
|
|
 |
| 14 |  |  An effective risk management plan will need to address which of the following issues? |
|  | A) | risk avoidance |
|  | B) | risk monitoring |
|  | C) | contingency planning |
|  | D) | all of the above |
|
|
 |
| 15 |  |  Risk monitoring involves watching the risk indicators defined for the project and not determining the effectiveness of the risk mitigation steps themselves. |
|  | A) | True |
|  | B) | False |
|
|
 |
| 16 |  |  Hazard analysis focuses on the identification and assessment of potential hazards that can cause |
|  | A) | project termination |
|  | B) | schedule slippage |
|  | C) | external problems |
|  | D) | entire system to fail |
|
|
 |
| 17 |  |  Risk information sheets (RIS) are never an acceptable substitute for a full risk mitigation, monitoring, and management (RMMM) plan. |
|  | A) | True |
|  | B) | False |
|
|