True/False Quiz
(See related pages)



1

Project champions are people who promote and support projects.
A)True
B)False
2

There can be two or more parallel critical paths, all having exactly the same completion time.
A)True
B)False
3

The term "work breakdown structure" refers to a failure in the work structure.
A)True
B)False
4

In crashing it may be necessary to shorten activities not on the critical path in order to accelerate the project.
A)True
B)False
5

In PERT, if the scheduled project completion time and sum of the average completion times for critical path activities are the same, the probability of completing the project on schedule is estimated at 50 percent, assuming no other paths are near-critical.
A)True
B)False
6

Early in a project's life cycle, risk occurrence has a high probability but a low cost.
A)True
B)False
7

Projects go through a life cycle that involves introduction, growth, maturity and decline.
A)True
B)False