Site MapHelpFeedbackMultiple Choice Quiz
Multiple Choice Quiz
(See related pages)

Section 1.1

1
Which question no longer concerns the modern software engineer?
A)Why does computer hardware cost so much?
B)Why does software take a long time to finish?
C)Why does it cost so much to develop a piece of software?
D)Why can't software errors be removed from products prior to delivery?

Section 1.1

2
Software is a product and can be manufactured using the same technologies used for other engineering artifacts.
A)True
B)False

Section 1.1

3
Software deteriorates rather than wears out because
A)Software suffers from exposure to hostile environments
B)Defects are more likely to arise after software has been used often
C)Multiple change requests introduce errors in component interactions
D)Software spare parts become harder to order

Section 1.2

4
WebApps are a mixture of print publishing and software development, making their development outside the realm of software engineering practice.
A)True
B)False

Section 1.3

5
Which of the items listed below is not one of the software engineering layers?
A)Process
B)Manufacturing
C)Methods
D)Tools

Section 1.4

6
Software engineering umbrella activities are only applied during the initial phases of software development projects.
A)True
B)False

Section 1.4

7
Which of these are the 5 generic software engineering framework activities?
A)communication, planning, modeling, construction, deployment
B)communication, risk management, measurement, production, reviewing
C)analysis, designing, programming, debugging, maintenance
D)analysis, planning, designing, programming, testing

Section 1.5

8
Planning ahead for software reuse reduces the cost and increases the value of the systems into which they are incorporated.
A)True
B)False

Section 1.5

9
The essence of software engineering practice might be described as understand the problem, plan a solution, carry out the plan, and examine the result for accuracy.
A)True
B)False

Section 1.6

10
In agile process models the only deliverable work product is the working program.
A)True
B)False

Section 1.7

11
A most software development projects are initiated to try to meet some business need.
A)True
B)False

Section 1.7

12
In general software only succeeds if its behavior is consistent with the objectives of its designers.
A)True
B)False